Simplifications to traffic routing and resurfacing to improve guest experiences
A long-awaited project to overhaul and update the Peoria Campus parking lots and traffic routing will clear up confusion and improve traffic flow for services, special events, guests and regular ministry activities.
- All inbound traffic will enter from Wilhelm Road.
- The Allen Road entrance will be closed for the duration of the project.
- For everyone's safety and convenience, please be courteous and cautious, and follow parking attendant instructions carefully.
Temporary Changes
See a visual overview of closures and traffic directions during construction.
Finished Project
Get a sneak peek of the finished campus enhancements.
Join the Parking Team
Your help is needed to ensure safety, efficiency, and positive experiences.
Got Questions?
For more information, contact Todd Parmenter, Executive Pastor of Operations.
Updates
Check here for periodic updates on project progress or other important updates.
July 23, 2021
July 22, 2021
June 9, 2021
May 24, 2021
Project timeline established
April 15, 2021
General Contractor retained and bids let
Northwoods Executive Pastor of Operations, Todd Parmenter, announced that O'Shea Builders has been retained as General Contractor for the project.